CONSTRUCTION OF THE GAS PIPELINE SECTION BORDER WITH BULGARIA – SKOPJE


First and biggest investment so far in the gas pipeline in Macedonia was started in 1992 by construction of the major gas network DN 530 mm – 97 km from the Bulgarian border to the capital city Skopje.

Chakar & Partners provided consulting services in the Investment construction of the gas network  in the Republic of Macedonia, for solving practical problems, organization and supervision in the:

– investment program

– preceding works

– drawing up of the plans

– preparation works

– main works and

– delivery of the object

Chakar & Partners as a subcontractor for construction, provided all necessary workers as a support to the Main contractor during the construction works.

The project has been successfully competed in the anticipated period, i.e. drawing up plans, expropriation project, expropriation and realization of the construction and installation works, access roads 80 km etc.

  1. major gas network DN 530 mm – 97 km
  2. usher gas network DN 200 – 430 mm
  3. measurement and regulation stations – 6 pieces